You did not sign it, but you own it. The acquired company's take or pay clause does what it says: if you do not take the product, you pay for it anyway. A minimum purchase commitment works the same way with a different name. The former owner agreed in a good year, or to win a price. The obligation continues after the sale, usually without anyone mentioning it.
These commitments do not appear on the income statement until they bite. They matter in an integration because integration moves volume. Consolidate suppliers and you may fall short of a commitment. Close a branch and you may stop buying what the contract assumes. The earlier review in vendor contracts that end on a change of control should have found the contracts. This page is about what to do with them.
Find and read every commitment
Check supplier contracts for minimum volumes, minimum dollar amounts, take or pay terms, annual commitments with penalties, and shortfall payments. Check equipment leases and service contracts for minimum fees. Check fuel, freight, and materials agreements.
For each, record the commitment, the period, the shortfall remedy, the current run rate, and the date it ends. A table you can sort by risk is worth the hour.
Compare commitments to your plan
Take the integration plan and ask which moves change volume with each supplier. Will you route more through their supplier or less? Will you close a site, a service line, or a customer segment that drives the purchases? Will your own contracts with the same supplier now overlap?
Run the numbers. A shortfall payment of a modest amount may be worth paying to proceed with a better plan. A large one may change the plan.
Options
Meet the commitment, by shifting volume to the supplier. Negotiate it down or out, using the relationship or other business as a trade. Combine the commitment with yours, so volume across both companies counts toward one target. Run it off, if the term is short. Or pay the shortfall deliberately.
Suppliers tend to prefer a revised commitment to a dispute. If you can offer a longer term, a broader product mix, or reliable payment, you may get a fair outcome. Rebates are a related question; see vendor rebate tiers after acquisition.
Watch the end dates
Put the expiry and notice dates on the tracker. Some contracts renew automatically unless notice is given by a particular date. Missing it can lock in another year of the commitment. Assign one person to own the calendar. I read every take or pay clause as a bill I have not been sent yet.
Decision table: what to do with an inherited commitment
Apply to each commitment on your list. Owner: the purchasing lead, with finance.
| Question | If yes, it points to | If no, it points to |
|---|---|---|
| Will the integration plan reduce volume below the commitment? | Quantify the shortfall and decide whether to adjust the plan or the contract | No shortfall expected. Still put the end date on the calendar |
| Can volume from the combined company meet the commitment? | Shift volume and count both companies toward it | You need a different answer: renegotiate, run it off, or pay |
| Is the supplier willing to renegotiate? | Trade term or product mix for a lower commitment | Run it off, or pay the shortfall on purpose if the plan is worth it |
| Is the term short? | Run it off and set a calendar reminder for notice | Consider paying the shortfall deliberately |
| Is the shortfall small next to the benefit of the plan? | Pay it and proceed | Revisit the plan |
A worked example of the shortfall math
Suppose the acquired company agreed to buy a stated quantity of a material each year and pays a fixed amount per unit of shortfall. Your plan closes one of its two warehouses and moves half the work to your site, which uses a different supplier. Purchases from the committed supplier drop by a third.
Compute the shortfall, multiply by the per unit charge, and compare it to the saving from the closed warehouse. If the saving is larger, close and pay, and note the charge as a cost of integration. If the saving is smaller, change the plan, or move your own purchases to the committed supplier to fill the gap, which may cost more than the shortfall itself.
In many cases the best result comes from a conversation with the supplier. Offer to take the combined volume of both companies for a longer period in exchange for waiving the shortfall. The supplier keeps the customer and the volume. You keep the plan. The calendar matters, so open that conversation well before the measurement period closes.
Put it in the model
The finance lead should include the commitments in the cash plan and the synergy ledger. A synergy that depends on moving volume away from a supplier with a commitment is not a synergy until the shortfall is counted. The point of the ledger is to separate what is bankable from what is aspirational.
For the framework for making these calls, turn to the post-merger integration playbook. Know what you owe before you move. For the add-on integration view, see integrating add-ons into a platform.
Get the 100 day integration tracker
The tracker puts an owner, a date, and a status on every integration task from pre-close to day 100, so decisions like this one get made on purpose and followed up.
One email with the download, and occasional Building Results notes. Opt out any time.
Questions
What do you do with purchase commitments the acquired company signed?
You own it. Find every minimum purchase and take or pay commitment, record the period, shortfall remedy, run rate, and end date, and compare them to your integration plan. Then meet the commitment by shifting volume, negotiate it down, combine volume across both companies, run it off, or pay the shortfall deliberately.
What is a take or pay clause?
A clause that requires you to pay for a set amount whether or not you take the product.
Can I renegotiate an inherited commitment?
Often, if you offer something the supplier values, such as a longer term or more business.
How do I track renewal dates?
Put them on the integration tracker with an owner. Automatic renewals are easy to miss.